Work on Upper Tamakoshi going at full swing

Published On: November 21, 2016 12:30 AM NPT By: Ramesh Khatiwada


DOLKHA, Nov 21: Work of Upper Tamakoshi Hydropower Project is going on in full swing.

Four turbines have already been installed and installation work of remaining two is at the final stage. Similarly, work to build foundation to install 19 transformers in the powerhouse is also in the last leg. 

The national pride project, which was affected for months by the earthquakes of 2015 and Indian blockade, has made significant progress in recent months.  

Talking to Republica, Purushottam Ranjit, engineer of Upper Tamakoshi Hydropower Ltd, said that the project has made astonishing progress. 

Sinohydro, the contractor for civil works, has already built four-storied power house which will have generators and turbine. We will start fitting equipment in the power houses after few weeks,” said Ranjit. “Work to build structure to install remaining two turbines will go simultaneously with hydro mechanical works.”

Chief of the project, Bigyan Prasad Shrestha, said that the work in pour house has progressed faster than his expectations. “Indian firm Texmaco Rail & Engineering Ltd has already started installing equipment in the power house," he added.

According to project official, work on a tunnel to the dam site is expected to complete within a month. The project has changed the design and decided to build a tunnel to the project site after a landslide triggered by the 2015 earthquakes away the access road to the dam site.

Nearly 89 percent of tunnel work between the dam site and the powerhouse has already been completed. Construction of the dam had been completed before the earthquake.

Officials expect that the project will complete by June 2018.

Similarly, work on the transmission line to evacuate electricity is also making good progress. Ganesh Neupane, spokesperson of the project, said that the construction of transmission line to connect the power to Khimti is moving ahead in the right direction. 

The power generated by the project will be supplied in the eastern region via Khimti Dhalkebar Transmission Line. A total of 63 out of 127 towers have already been erected and all the equipment needed for installation have already been transported to the project site, according to the project officials. 

Cost escalates to Rs 45 billion
Delays due to earthquake and blockade as well as variation in tunnel works and depreciation of Nepali currency vis-à-vis US dollar in recent years have increased the project cost to Rs 45 billion from the initial estimate of Rs 35 billion in 2011, according to the project officials.


Leave A Comment