February 11, 2018 02:17 am
DARCHULA, Feb 10: The 30 MW Chameliya Hydroelectric Project started generating electricity from Saturday. The project which saw several cost variations, controversies and frustrations over delays has now been connected to the national grid, nearly 11 years after works started in January, 2007. The peaking run of river project, which can generate minimum six hours in full capacity, was supposed to complete in May 2011. The project started for a regional balance in electricity generation is believed to be a landmark in Province 7.
February 10, 2018 14:53 pm
DARCHULA, Feb 10: Prime Minister Sher Bahadur Deuba has inaugurated Chameliya Hydropower, a national pride project based at Balach, Shailya Shikhar Municipality-1 of the district on Saturday.
February 9, 2018 15:43 pm
DARCHULA, Feb 9: Construction task of 30-MW Chameliya hydropower project has been completed. The 30-Megawatt-capacity project is constructed at a cost of Rs 16 billion with government investment.
December 13, 2017 08:00 am
BAITADI/ DARCHULA, Dec 13: Chameliya hydroelectric project is finally ready to supply electricity, after 10 years of its inception. The project completed test production last week, and is planning to begin supplying within a month.
October 5, 2017 07:49 am
KATHMANDU, Oct 5: The long-delayed Chameliya Hydroelectric Project (30 MW) is finally starting generation by the end of December.
October 5, 2017 05:09 am
KATHMANDU, Oct 5: The long-delayed Chameliya Hydroelectric Project (30 MW) is finally starting generation by the end of December.
September 23, 2016 03:00 am
KATHMANDU, Sept 23: Minister of Energy Janardan Sharma on Thursday directed the contractor of the Chameliya Hydropower Project to complete the project in 10 months.